Insight · Regulatory
Insight No. 02 · Regulatory

The rulebook is turning toward on-site power.

In June 2026, federal regulators told all six U.S. grid operators to make room for behind-the-meter generation and co-located load — and to stop spreading large-load grid costs onto everyone else. Here is what it changes for how AI campuses get powered.

The one-line answer

FERC found existing large-load grid rules unjust and unreasonable and ordered all six market operators to reform them within 60 days. Of five mandated reform areas, one names co-location and behind-the-meter generation outright. The regulated path to powering AI is shifting from “wait in the queue” to “bring your own power.”

6 grid operators
PJM, MISO, SPP, CAISO, ISO-NE & NYISO — each given 60 days to justify or reform large-load tariffs
5 reform areas
One names behind-the-meter generation and co-location; another targets cost-shifting onto other customers
~2/3 of U.S. load
The share of electricity demand served in the regions covered by the orders

What FERC actually ordered — and what each piece signals

The Commission directed every grid operator to address five reform areas. Read together, they describe a system being re-engineered to favor power that is generated where it is consumed.

The reform FERC mandatedWhat it signals for on-site power
Faster transmission study processes, including alternative technologiesEven the regulator concedes the interconnection queue is the bottleneck — and that alternatives to grid upgrades deserve a faster lane.
Prevent cost-shifting; require transparency into transmission costsThe load that triggers a grid upgrade increasingly owns its cost — raising the real price of grid-dependent power for large users.
Accommodate co-location and behind-the-meter generationOn-site generation moves from improvised workaround to a tariffed, regulated option the grid operators must support.
New transmission services for flexible large loadsLoads that can modulate are now formally valued — rewarding storage and intelligent dispatch over rigid demand.
Study generation alongside electrically-proximate large loadsPairing generation directly with nearby load is recognized as a way to avoid costly, slow transmission build-outs.

Two shifts, both pointing the same way

Shift 01

Grid power gets more expensive — and more attributed

By moving to curb cost-shifting, FERC pushes the cost of the network upgrades a large load triggers back onto that load. Grid-dependent power for a hyperscale campus stops being a socialized cost and becomes a line item the project owns.

Shift 02

On-site power gets a cleared lane

For the first time, the federal regulator is directing grid operators to build rules that accommodate behind-the-meter generation and co-located load. What used to be a way around the system is becoming a recognized path through it.

Read the fine print

This is FERC-jurisdictional territory — PJM, MISO, SPP, CAISO, ISO-NE and NYISO — not ERCOT, so the effect is sharpest in Eastern markets, where PJM is already operationalizing co-located transmission service. And it cuts both ways: FERC also wants to speed interconnection, so a raw “queue-length” advantage may narrow over time. The durable edge is cost certainty and independence from the grid altogether.

Where AnchorPower Fits

The regulatory current now runs with the model, not against it.

AnchorPower was built to deliver firm, contracted power on-site — behind the meter, independent of the interconnection queue. The June 2026 reforms move the regulated market toward exactly that posture, whether a customer steps outside the grid entirely or co-locates within the new framework.

AnchorFirm → outside the system

Fully off-grid, behind-the-meter firm power steps outside the transmission system and these tariffs entirely — no queue, no network-upgrade cost allocation. First power in 18–20 months on a fixed-price PPA.

AnchorFlex & AnchorBridge → inside the framework

Grid-tied configurations operate within the co-location rules FERC is now standardizing — with the load flexibility that the new “flexible large load” transmission services are designed to reward.

Sources: FERC June 18, 2026 open meeting — show-cause orders (Items E-7 through E-12) and PJM co-location order on rehearing (Item E-2). See ferc.gov for the official orders. This page is commentary, not legal advice; jurisdiction and tariff treatment vary by region and project.
Pragmatic · Firm on site · Future-proof · DC-grade power
© 2026 AnchorPower Energy. All rights reserved.