Pragmatic · Firm on site · Future-proof · DC-grade power

The best
interconnection queue
is no queue at all.

AnchorPower Energy delivers and orchestrates firm capacity to Edge data-center compute facilities in 18 months — not 7 years.

5–7+ yrs
18 mo
GRID INTERCONNECTION QUEUEANCHORPOWER — FIRST POWER
18 mo
First power delivery, co-located behind the meter
<1.1
Target PUE — native DC architecture
~4%
Conversion loss vs. up to 30% on legacy AC
15 yr
Take-or-pay PPA · zero fuel · zero stranding
What We Do

We deliver contracted, co-located firm power that bypasses the grid entirely.

01

Fastest time-to-power

Behind the meter. No queue.

Behind-the-meter power eliminates grid interconnection entirely. No queue. No interconnection study. No utility delays. First power in 18 months — versus 5–7+ years on the grid queue.

02

Genuinely DC. Lossless. Firm.

Native DC architecture.

Moving from legacy AC to native DC eliminates the cost and heat of multiple conversion stages — cutting energy loss from as much as 30% to roughly 4%. Future-proof 400V / 800V power, purpose-built for compute loads, targeting a PUE below 1.1.

03

Zero fuel. Zero stranding.

Pure infrastructure economics.

No gas risk. No fuel-cost escalation. No pipeline risk. Long-term take-or-pay PPAs lock in revenue for 15 years. The customer takes demand risk; we take weather risk.

04

Modular & pre-fabricated

Containerized. Rapid.

Modular, containerized deployment lowers labour constraints and enables rapid build — cutting design, permitting, and construction time. Most of the system arrives pre-fabricated.

The Grid Queue Is the New Bottleneck

Can your AI roadmap afford a 7-year wait?

Grid interconnection
5–7+ years
  • PJM / ERCOT / SPP queue · interconnection studies
  • Merchant price risk + fuel-cost escalation
  • 300+ GW gas in development — only 5–8 GW contracted
AnchorPower — AnchorFirm
18–20 months
  • Co-located · private PPA · zero queue risk
  • 15-year take-or-pay PPA · zero fuel cost
  • Zero stranding risk · cost curve continues falling
The Insight

Gas isn't the answer. It's the next stranded-asset bubble.

The U.S. now leads the world for gas-power development — over 1,000 GW planned. But under the surface, only 5–8 GW is contracted to a creditworthy off-taker. The rest is speculative, dependent on AI demand holding and turbine makers delivering on time.

Sources: Global Energy Monitor (Jan 2026), Utility Dive on GE Vernova (Dec 2025), Canary Media.
Signed / committed off-take7
GE Vernova backlog (sold out '29)80
Of which: data-center linked100
U.S. gas in development330
Battery-firmed solar + firming is faster, cheaper, and bankable.
What We Offer

One flagship. Two configurations. Every site has a path.

AnchorFirm is the primary product — the fully off-grid configuration. AnchorFlex and AnchorBridge adapt to sites whose load profile or timeline needs a different shape.

Flagship

AnchorFirm

No grid. No queue. Firm on site.

The fully off-grid configuration. On-site solar PV, BESS, firming and LDES* with optional backup deliver firm, contracted power to a distributed 50–100 MW Edge data-center site under a 15-year take-or-pay PPA. No grid interconnection. Modular and containerized — first power in 18–20 months.

* LDES integration targeted post-2028
Secondary

AnchorFlex

Hybrid on-site + optional grid.

The same co-located generation stack with an optional utility tie — for flexible loads, seasonal balancing, or regions where a grid connection is available but non-critical.

Tertiary

AnchorBridge

Interim on-site power.

Bridging power for operators who cannot wait out the queue. Modular behind-the-meter generation and storage covers the gap between construction complete and permanent energization.

ACE Engine

An AI agent that dynamically schedules GPU workloads against available on-site generation and storage — maximizing compute per dollar, across multiple sites.

How We Work

Setting a new standard for contracted infrastructure.

01

Core architecture

We build what the system requires — long-term reliability and redundancy, efficiency (DC power for DC systems), optimal voltage at 400V → 800V, closed-loop water, and modular pre-fabricated systems.

02

Parallel-path development

From modular power to containerized deployment, our systems are engineered and procured simultaneously with permitting and landowner negotiations — compressing the traditional 3–5 year pipeline to 12–14 months pre-construction.

03

15-year take-or-pay delivery

First power in 18–20 months under a negotiated take-or-pay PPA. The customer commits to capacity payments regardless of utilization. AnchorPower operates the asset and absorbs weather and production risk. No utility dependency, no FERC study, no interconnection queue — ever.

04

Adjacency-first siting

We can build in any U.S. state. We design custom power-delivery architectures matched to each customer's load profile and reliability requirements. Active proof-of-concept siting across Texas, Arizona, and Alberta.

Why Now

The window is open today.

$650B

Data-center AI capex in 2026 alone (Goldman Sachs). Power is the single largest unresolved constraint.

300+ GW

Gas in development; only 5–8 GW contracted. 60–75% stranded-asset probability by 2028–32 if AI demand softens.

20–40%

PPA premium operators will pay for speed and firmness — 18-month delivery vs. a 7-year grid queue.

Q3 2026

When operators finalize their 2027–28+ power strategies. The time to be at the table is now.

Intelligence & Market Validation

Seven signals. One direction.

May 2026Community OppositionOpposition to grid-tied data-center builds accelerates — reinforcing the case for distributed, behind-the-meter power.
Mar 2026Market SignalHyperscalers commit $650B AI capex — power now the #1 unresolved constraint (Goldman Sachs).
Feb 2026Industry ValidationSemiAnalysis: "the grid is old and tired" — new capacity must come from behind-the-meter sources.
Jan 2026Regulatory CatalystExecutive mandate accelerates data-center self-provisioning — reducing utility-dependency requirements.
Dec 2025Technology ProofCrusoe / Redwood Sparks: 99.2% standalone reliability on a 5.25-hour battery — validating the firm-storage thesis.
Nov 2025Gas Stranding RiskCanary Media: speculative gas infrastructure faces 60–75% stranding probability if AI demand underperforms.
Oct 2025LDES MilestoneForm Energy iron-air battery reaches commercial deployment readiness — 100-hour duration, $20/kWh target.
Who We Are

Built by professionals, not analysts.

AK

Ayaz Khokhar

Founder & CEO

Power and infrastructure executive and entrepreneur focused on energy development, construction, financing, and operations. Previously founded Source3 Energy and Source3 Energy X — GW-scale renewable and hydrogen development platforms — and GridWise AI, an AI-powered grid intelligence platform. B.S. Mechanical & Aerospace Engineering, University at Buffalo; MBA, Kellogg School of Management, Northwestern University.

IP

Imtiyaz Pirmohamed

Head of Development · P.Eng., B.S., MBA

Renewable energy infrastructure professional with 20+ years across utility-scale solar, microgrids, BESS, LDES, hydrogen and fuel cells — developing grid-connected and independent power projects globally and at Source3 Energy. B.S. Electrical Engineering, University of Central Florida; MBA, University of Groningen. Professional Engineer, Ontario, Canada.

Ehteshaam Fahim

Lead — Construction & Delivery

Fahad Ahmad

Lead — Corporate Development & Project Finance

Peter Schimmann

Legal & Contracts
Advisory Board
  • Former product line owner, Tesla MegaPack
  • Former renewable infrastructure project finance executive, BP / Brookfield
  • Former C-suite executive, ATCO Renewables

Let's get to work.

If power is the constraint on your compute roadmap, we should talk. AnchorPower delivers firm capacity where and when you need it.

Pragmatic · Firm on site · Future-proof · DC-grade power
© 2026 AnchorPower Energy. All rights reserved.