The best
interconnection queue
is no queue at all.
AnchorPower Energy delivers and orchestrates firm capacity to Edge data-center compute facilities in 18 months — not 7 years.
We deliver contracted, co-located firm power that bypasses the grid entirely.
Fastest time-to-power
Behind-the-meter power eliminates grid interconnection entirely. No queue. No interconnection study. No utility delays. First power in 18 months — versus 5–7+ years on the grid queue.
Genuinely DC. Lossless. Firm.
Moving from legacy AC to native DC eliminates the cost and heat of multiple conversion stages — cutting energy loss from as much as 30% to roughly 4%. Future-proof 400V / 800V power, purpose-built for compute loads, targeting a PUE below 1.1.
Zero fuel. Zero stranding.
No gas risk. No fuel-cost escalation. No pipeline risk. Long-term take-or-pay PPAs lock in revenue for 15 years. The customer takes demand risk; we take weather risk.
Modular & pre-fabricated
Modular, containerized deployment lowers labour constraints and enables rapid build — cutting design, permitting, and construction time. Most of the system arrives pre-fabricated.
Can your AI roadmap afford a 7-year wait?
- PJM / ERCOT / SPP queue · interconnection studies
- Merchant price risk + fuel-cost escalation
- 300+ GW gas in development — only 5–8 GW contracted
- Co-located · private PPA · zero queue risk
- 15-year take-or-pay PPA · zero fuel cost
- Zero stranding risk · cost curve continues falling
Gas isn't the answer. It's the next stranded-asset bubble.
The U.S. now leads the world for gas-power development — over 1,000 GW planned. But under the surface, only 5–8 GW is contracted to a creditworthy off-taker. The rest is speculative, dependent on AI demand holding and turbine makers delivering on time.
One flagship. Two configurations. Every site has a path.
AnchorFirm is the primary product — the fully off-grid configuration. AnchorFlex and AnchorBridge adapt to sites whose load profile or timeline needs a different shape.
AnchorFirm
The fully off-grid configuration. On-site solar PV, BESS, firming and LDES* with optional backup deliver firm, contracted power to a distributed 50–100 MW Edge data-center site under a 15-year take-or-pay PPA. No grid interconnection. Modular and containerized — first power in 18–20 months.
AnchorFlex
The same co-located generation stack with an optional utility tie — for flexible loads, seasonal balancing, or regions where a grid connection is available but non-critical.
AnchorBridge
Bridging power for operators who cannot wait out the queue. Modular behind-the-meter generation and storage covers the gap between construction complete and permanent energization.
An AI agent that dynamically schedules GPU workloads against available on-site generation and storage — maximizing compute per dollar, across multiple sites.
Setting a new standard for contracted infrastructure.
Core architecture
We build what the system requires — long-term reliability and redundancy, efficiency (DC power for DC systems), optimal voltage at 400V → 800V, closed-loop water, and modular pre-fabricated systems.
Parallel-path development
From modular power to containerized deployment, our systems are engineered and procured simultaneously with permitting and landowner negotiations — compressing the traditional 3–5 year pipeline to 12–14 months pre-construction.
15-year take-or-pay delivery
First power in 18–20 months under a negotiated take-or-pay PPA. The customer commits to capacity payments regardless of utilization. AnchorPower operates the asset and absorbs weather and production risk. No utility dependency, no FERC study, no interconnection queue — ever.
Adjacency-first siting
We can build in any U.S. state. We design custom power-delivery architectures matched to each customer's load profile and reliability requirements. Active proof-of-concept siting across Texas, Arizona, and Alberta.
The window is open today.
Data-center AI capex in 2026 alone (Goldman Sachs). Power is the single largest unresolved constraint.
Gas in development; only 5–8 GW contracted. 60–75% stranded-asset probability by 2028–32 if AI demand softens.
PPA premium operators will pay for speed and firmness — 18-month delivery vs. a 7-year grid queue.
When operators finalize their 2027–28+ power strategies. The time to be at the table is now.
Seven signals. One direction.
Built by professionals, not analysts.
Ayaz Khokhar
Power and infrastructure executive and entrepreneur focused on energy development, construction, financing, and operations. Previously founded Source3 Energy and Source3 Energy X — GW-scale renewable and hydrogen development platforms — and GridWise AI, an AI-powered grid intelligence platform. B.S. Mechanical & Aerospace Engineering, University at Buffalo; MBA, Kellogg School of Management, Northwestern University.
Imtiyaz Pirmohamed
Renewable energy infrastructure professional with 20+ years across utility-scale solar, microgrids, BESS, LDES, hydrogen and fuel cells — developing grid-connected and independent power projects globally and at Source3 Energy. B.S. Electrical Engineering, University of Central Florida; MBA, University of Groningen. Professional Engineer, Ontario, Canada.
Ehteshaam Fahim
Fahad Ahmad
Peter Schimmann
- Former product line owner, Tesla MegaPack
- Former renewable infrastructure project finance executive, BP / Brookfield
- Former C-suite executive, ATCO Renewables
Let's get to work.
If power is the constraint on your compute roadmap, we should talk. AnchorPower delivers firm capacity where and when you need it.